1. For new blocks, the approved work must be completed within 4 months from the date of the permit.
2. For existing blocks, the approved work must be completed within 1 month from the date of the permit.
3. No Work shall be carried out before 8 am or after 6 pm.
4. Noisy Work such as cutting of tiles, demolition of walls and removing floor/wall finishes are restricted from 9.00 am to 5.00 pm during the weekdays. Such work are not allowed on Saturdays, Sundays and Public Holidays.
5. At any one time, only two of the approved hand-held power tools or their approved equivalents are allowed to be used.
6. Renovation contractors are not allowed to take more than three consecutive days to demolish walls and/or removal of wall/floor finishes.

max ng

Posts : 5
Join date : 2011-08-03

View user profile

Back to top Go down

View previous topic View next topic Back to top

- Similar topics

 
Permissions in this forum:
You cannot reply to topics in this forum